Online College Courses for Credit

+
CPMGT 303 WEEK 3 Project Estimating Schedule and Summary

CPMGT 303 WEEK 3 Project Estimating Schedule and Summary

Rating:
Rating
(0)
Author: Yanis Gherasim
See More
Fast, Free College Credit

Developing Effective Teams

Let's Ride
*No strings attached. This college course is 100% free and is worth 1 semester credit.

38 Sophia partners guarantee credit transfer.

299 Institutions have accepted or given pre-approval for credit transfer.

* The American Council on Education's College Credit Recommendation Service (ACE Credit®) has evaluated and recommended college credit for 33 of Sophia’s online courses. Many different colleges and universities consider ACE CREDIT recommendations in determining the applicability to their course and degree programs.

Tutorial

CPMGT 303 WEEK 3 Project Estimating Schedule and Summary

 

Buy Solutions: http://hwsoloutions.com/downloads/cpmgt-303-week-3-project-estimating-schedule-and-summary/

CPMGT 303 WEEK 3 Project Estimating Schedule and Summary

CPMGT 303 WEEK 3 Project Estimating Schedule and Summary

Review the Microsoft® Project Quick Start guide.

Continue using the organization and project selected in Week 2 for this assignment.

Create the following in Microsoft® Project using the Microsoft® Project 2016 Student Desktop:

Input the activities in Microsoft® Project needed to complete the project, linking each activity in the order that the activity can be done, regardless of any known resource constraints.

Ensure activities are linked to project deliverables.

Identify resources required to complete the project. Input these resources and each resource estimated costs into Microsoft® Project Resource Sheet. For labor this may be done with hourly rate or one-time consultant fee depending on the activity.

Assign resources to each of the activities in Microsoft® Project.

Estimate the time it will take each resource, to complete each activity (for example, in hours, days, or weeks) and input into Microsoft® Project.

Use Microsoft® Project to identify the project’s critical path.

Write a 350- to 700-word summary describing the process you followed in identifying the critical path, as well as any lessons learned.

Submit your Microsoft® Project schedule and Microsoft® Word summary.

Click the Assignment Files tab to submit your assignment.

CPMGT 303 WEEK 3 Project Estimating Schedule and Summary

CPMGT 303 WEEK 3 Project Estimating Schedule and Summary

Review the Microsoft® Project Quick Start guide.

Continue using the organization and project selected in Week 2 for this assignment.

Create the following in Microsoft® Project using the Microsoft® Project 2016 Student Desktop:

Input the activities in Microsoft® Project needed to complete the project, linking each activity in the order that the activity can be done, regardless of any known resource constraints.

Ensure activities are linked to project deliverables.

Identify resources required to complete the project. Input these resources and each resource estimated costs into Microsoft® Project Resource Sheet. For labor this may be done with hourly rate or one-time consultant fee depending on the activity.

Assign resources to each of the activities in Microsoft® Project.

Estimate the time it will take each resource, to complete each activity (for example, in hours, days, or weeks) and input into Microsoft® Project.

Use Microsoft® Project to identify the project’s critical path.

Write a 350- to 700-word summary describing the process you followed in identifying the critical path, as well as any lessons learned.

Submit your Microsoft® Project schedule and Microsoft® Word summary.

Click the Assignment Files tab to submit your assignment.

CPMGT 303 WEEK 3 Project Estimating Schedule and Summary