Creating a WBS

Author: Sophia

what's covered
In this lesson, we'll discuss how to create a Work Breakdown Structure (WBS) by focusing on:

Table of Contents

1. Work Breakdown Structure (WBS)

As you may know, the WBS is a method that a project manager uses to organize project work and break it down into manageable chunks.

Work Breakdown Structure

It's the goal of the WBS to provide a complete picture of the work involved to create the project deliverables. The WBS is thus the foundation for the project schedule, resource planning, and the determination of project budget.

IN CONTEXT
You are the project manager for a house construction project. The creation of a WBS must be a collaboration between you and the members of the project team or others who have knowledge of the work.

Any individuals on the project team who have responsibility for the work toward deliverables should be involved. This includes all the trades that are part of the construction, such as those who create the structure of the house, install the roof, or place the plumbing and electrics.

Members of Project Team House
Subject Matter Experts
Experienced Individuals from Similar Projects
WBS and Schedules from Similar Projects

Subject matter experts should also be involved. These are individuals with specialized knowledge that relates to the project goals or deliverables. When building an energy efficient house, subject matter experts may not work on the project, but might just provide advice that defines the work.

Any individuals who have experience with similar projects should be consulted and the project manager should review the WBS or schedules for any projects that have similar deliverables.

hint
It would be simple to copy the WBS tasks from projects that have been completed successfully, and then modify the WBS for your specific project.

Once the project manager knows who will collaborate on the WBS, it's time to break down the work.


2. Sticky Note Method

A WBS is often represented as a hierarchy and one method that works well to create it is called the sticky note method. In this method, each element of the WBS is written on a sticky note. These notes can then be easily moved around as more information comes in from collaborators.

This works better than a document or a whiteboard because the structure is more flexible. Since the notes can be easily moved, collaborators do not feel locked into certain workflows during the brainstorming process.

2a. Project Name

The first sticky note will have the name of the project. Let's continue with the project of building a house. So our first sticky notes may have "Dream Home" written on it to represent the name of our project.

Project Name

2b. Deliverables

The first level of the hierarchies is project deliverables. While these should usually be defined in the project scope, occasionally new project deliverables will be identified during the WBS process. If new project deliverables emerge, be sure to modify the project scope and notify the stakeholders of the change.

For the house project, the scope is taken from the house plans. Perhaps you are in charge of building a single story, 1,500 square foot ranch home.

Deliverable

term to know
Project Deliverables
Defined outcomes that are the focus of a project and are the basis for all project activities.

2c. Activities

The next level is project activities. These are the major pieces of work necessary to create the deliverables, and they are generally expressed as verbs.

For the house project, these can be listed as:

Activities

Each activity will then be broken down further into tasks.

term to know
Project Activities
Work elements that are required to complete or manage a project.

2d. Tasks

Project tasks are the specific work needed to complete an activity. Unlike activities, however, project tasks will be assigned to the individuals performing the work.

For the house project, once the foundation activity is complete, there are corresponding tasks such as:

Tasks

This continues for each activity, breaking down the work into tasks that can be assigned.

term to know
Project Tasks
Discrete work that is required to complete project activities.

2e. Sequence

Once all the tasks have been identified, the proper sequence of the WBS needs to be confirmed. The WBS must represent the correct order. The sticky note method makes it easy to move these project tasks to their proper locations.

With the house project, the water lines must be installed before the concrete is poured, so this needs to be moved to the proper location.

Work Breakdown Structure

2f. Review

The last step is to review the work breakdown structure. For any type of project, it is important to analyze and verify the work, ensure the sequence is logical for the work that is being done, and make sure nothing is missing.

summary
In this lesson, you learned how to create a Work Breakdown Structure (WBS) using the collaboration process. You now know that the Work Breakdown Structure breaks down into deliverables, activities, and tasks. Additionally, you learned how to use the sticky note method during the process and how activities break down further into tasks.

Terms to Know
Project Activities

Work elements that are required to complete or manage a project.

Project Deliverables

Defined outcomes that are the focus of a project and are the basis for all project activities.

Project Tasks

Discrete work that is required to complete project activities.