+
PROJ586 Final Exam Set 2

PROJ586 Final Exam Set 2

Rating:
Rating
(0)
Author: Christine Farr
Description:

http://www.devrygenius.com/product/proj586-final-exam-set-2

1. (TCO A) In a _____ organization, the project manager does not have complete authority over the project team. (Points : 5)
autonomous project
matrix
functional
functional and matrix
2. (TCO H) What is the longest phase of the project life cycle? (Points : 5)
Initiating
Planning
Performing
Closing
3. (TCO B) A(n) _____ is defined as a piece of work that consumes time. (Points : 5)
work package
activity
element
work object
4. (TCO D) All of the following are risk response types except _____. (Points : 5)
acceptance
transference
an opportunity
avoidance
5. (TCO F) The two most common types of project reports are _____. (Points : 5)
progress reports and the contract report
weekly and monthly
progress reports and the final report
update-only reports and status
6. (TCO C) The _____ time is the latest time by which a particular activity must be finished in order for the entire project to be completed by its required completion time. (Points : 5)
earliest start
earliest finish
latest start
latest finish
7. (TCO G) Which of the following is not an advantage of using project management software? (Points : 5)
Accuracy
The learning curve
Speed
Record keeping
8. (TCO A) Projects are identified and selected in the _____. (Points : 5)
initiating phase
planning phase
performing phase
closing phase
9. (TCO C) In addition to showing the technical constraints among activities, how does the network diagram logic also take into account resource constraints? (Points : 5)
Activities that use the same resource may not be able to occur in parallel to each other.
Activities that use different resources may be shown in a serial relationship.
The activities could be shown in a loop relationship.
Resources that are unlimited are not shown in a resource assignment.
10. (TCO F) The budget for each work package is _____. (Points : 5)
charged completely on the first day of the work package
charged at the end of the project
distributed over the duration of the work package
charged completely on the last day of the work package


(more)
See More
Try a College Course Free

Sophia’s self-paced online courses are a great way to save time and money as you earn credits eligible for transfer to over 2,000 colleges and universities.*

Begin Free Trial
No credit card required

25 Sophia partners guarantee credit transfer.

221 Institutions have accepted or given pre-approval for credit transfer.

* The American Council on Education's College Credit Recommendation Service (ACE Credit®) has evaluated and recommended college credit for 20 of Sophia’s online courses. More than 2,000 colleges and universities consider ACE CREDIT recommendations in determining the applicability to their course and degree programs.

Tutorial