Use Sophia to knock out your gen-ed requirements quickly and affordably. Learn more
×

Project Budgeting

Author: Sophia

what's covered
This lesson provides an overview of determining a project budget including:

Table of Contents

1. Real and Overhead Project Costs

Budgeting is an important skill to learn. In addition to an accurate schedule, a project must also have a predictable project budget. The full cost to complete a project must be documented.

The total cost of a project is the sum of two separate categories:

  • Real project costs
  • Overhead costs
Real project costs are those items paid for directly out of the project budget. This includes any resources that will be used to complete the project deliverables, such as materials, labor, vendor, or supplier expenses, and equipment.

EXAMPLE

The people who program software during a web development project would be considered a real project cost.

Overhead costs can come from resources that help create the project deliverable. If those resources have a long term value to the organization beyond the project, the organization might pay the cost instead of the project.

EXAMPLE

Electricity is needed to run a machine needed on a project. The cost of that electricity is overhead.

EXAMPLE

Computers used by programmers during a web development project will be used after the project, so the organization decides they will pay for the computers. The computers are considered overhead costs.

Including overhead costs in the total project cost gives an organization a full accounting for a project. However, since the overhead costs do not impact the money that needs to be allocated to a project and tracked by the project manager, it's reasonable not to include overhead cost, too.

It's up to the organization or the individual project manager whether to include overhead costs in the project budget.

term to know
Project Budgeting
The process to identify the cost of completing a project.


2. Budgeting Building Resources

The project manager reviews various information to build the budget.

Project scope should be reviewed for any budget requirements.

Effort estimates in the project schedule will be used to budget for resources. Any equipment or other resources needed to complete activity should also be included.

hint
Review budgets from previous projects to find details that might be missed.


3. Budgeting for Effort

When budgeting the effort estimates on tasks, the project manager includes the cost for all people resources. These estimates directly reflect the labor cost needed to complete the project.

IN CONTEXT
In the schedule shown, there are two people resources used to complete the work on the customer complaint form for the web development project.

TASKS EFFORT
Program Customer Complaint Form Stephen: 16 Hours
Jon: 8 Hours

Stephen will spend 16 hours on the task and John will spend eight hours. In order to arrive at a budget number for this task, those hours are multiplied by the cost per hour of a resource. Let's assume this cost is $45 per hour in our organization.

Budget for Stephen = 16 Hours X $45 Per Hour = $720
Budget for Jon = 8 Hours X $45 Per Hour = $360

The cost calculation on this task for Steven is $720 and John's cost on this task is $360. To find the budget for this task, add Steven's cost and John's cost to get a total of $1,080.

Budget for Task = $1,080

This is then done for each task on a project. In some instances, the budget is done before the schedule. In those cases, when the schedule is complete, it should be reviewed to validate if the budget was accurate. Individual efforts in the schedule might be real costs to the project, or they might be overhead costs.

hint
The project manager should always include real costs in the budget.


4. Budgeting for Non-People Resources

Any non-people resources, such as materials or equipment used to complete the project deliverables, are also budgeted in a project. Fixed cost for supplier support or consultants should also be included in these costs.

Computer Phone Desk

As with other costs, the project manager should determine if each non-people resource cost is a real or overhead cost, and whether to include them in the project budget.

summary
You've learned about real cost and overhead cost in a project budget. Real costs are costs associated directly and only within the project. Overhead costs are costs paid by the organization or company as a whole. You know that when building a budget, costs for people and non-people resources, must be considered. And budgeting for the labor of people resources is deemed as “budgeting for effort”.

Source: This work is adapted from Sophia Author Jeff Carroll.

Terms to Know
Project Budgeting

The process to identify the cost of completing a project.