It's the project manager's responsibility to determine the time that it will take to complete all work included in the Work Breakdown Structure (WBS), and this is done through the project schedule.
When the schedule is complete, it should reflect the sequence in which work will proceed, who will perform the work, and the time required to complete all the deliverables.
EXAMPLE
A group must modify an organization's website to add the ability for a customer to submit a complaint form. A few of the tasks may be survey customers, design modules, design form, program modules, program form, and test form.When creating the schedule for a project, four interrelated factors will require research and management associated with all the tasks.
With people resources, it is important to ask the following questions:
Time is the duration of the tasks in calendar days. Time estimating is the process of estimating the duration of each task or activity.
Effort is the actual hours, days, or weeks required to complete the task. Effort estimating is the process to determining the amount of labor (hours) that is required to complete each task or activity.
EXAMPLE
A task takes eight hours to complete, but the resource can only devote four hours per day. The effort on the task would be the eight hours, but the time on the task would be two days.Dependencies change the schedule when added, and involve questions such as:
Higher quality often results in more time spent on task, so this must be considered before the schedule is finalized. Therefore, the following questions to ask regarding quality are:
Once resources have been assigned to tasks, and estimates have been received from those resources for the time and effort involved to finish the work, then the initial schedule is complete.
At this stage, the project manager must review the schedule and attempt to identify any outstanding issues. A project manager should ask the following questions:
When questions are answered positively, a schedule is fully complete, and the project manager must then present it to the stakeholders and the team members.
Because it might be difficult for others to visualize how the work will proceed, the project manager should use methods to make the schedule more understandable.
One such method is a Gantt chart, which displays the sequence of activities, dependencies, and resources assignments in a visual manner that is easier to understand.
For our example project, a Gantt chart might look like this:
For some stakeholders and team members, the project manager might create an even simpler version of the schedule that has only high-level tasks and activities. The project manager might also give team members only the portion of their schedule that contains the task for which they're responsible.