A Gantt chart is a chart used to display all the work, the resources assigned, and the dependencies in the schedule.
As you can see in the example below, the Gantt chart visually represents the schedule as boxes to show a logical flow through the project.
This chart makes it simple to see who's working on a task, how long that task will take, and what tasks must be completed before and after the current work.
Some project managers will use the Gantt chart to build the schedule, and often continue to use it throughout the project.
The network diagram shows the flow of work between tasks or project units, and each unit is represented as a node on a network.
The start and end of the project are represented as circles, tasks are shown as boxes, and arrows show the dependencies between the tasks. Note how Task 3 cannot begin until Task 1 and Task 2 are both complete.
A network diagram should be used when there are multiple dependencies between tasks that might be too complicated for a Gantt chart to display.
A critical path will run through both a Gantt chart and a network diagram, and is the longest string of continuous dependent tasks.
This path represents the shortest amount of time in which a project can be completed; project managers identify critical paths because attempts to shorten the schedule need to occur by modifying tasks along this path.
In the image above, you can see that the project has two critical paths: Activities B and C, and Activities A, D, and F. Both paths show a minimum project time of seven months.
It is important to note that any delay in the tasks on the critical path will cause the schedule to increase in length. Think about the most recent project you worked on. With this project in mind, choose one of the three methods you just learned, and try to create a visual project schedule.